Which of the following is the BEST reason to use a burndown chart?
A. To determine how much risk is still associated with the project
B. To present the risks in criticality rating
C. To establish a backlog for project deliverables
D. To create a project charter
A. To determine how much risk is still associated with the project
B. To present the risks in criticality rating
C. To establish a backlog for project deliverables
D. To create a project charter