CompTIA Project+ PK0-004 – Question664

Which of the following is performed during the monitoring and controlling phase?

A.
Quality control and training plan development
B. Creation of schedule and fund deliverables
C. Development of transition plan and finalizing contracts
D. Quality assurance and governance oversight

Correct Answer: D