CompTIA Project+ PK0-004 – Question694

A newly developed claims processing system will require users of the prior system to be trained to use the new system. During which of the following project phases should the training occur?

A.
Closing
B. Executing
C. Planning
D. Monitoring and controlling

Correct Answer: B

Explanation: