CompTIA Project+ PK0-004 – Question698

A construction company has not been on the job for more than two weeks. Which of the following is an example of how a project manager can utilize the transfer risk strategy?

A.
Changing the schedule to accommodate a new finish date
B. Hiring a new company to complete the work
C. Calling the project sponsor to explain the situation
D. Requiring the construction company to send new employees

Correct Answer: B