A project is due to deliver, configure, and install a collection of medical devices. The first device in the collection is reportedly four weeks behind schedule is manufacturing. Which of the following BEST describes how the project manager can keep the project on track?
A. Expedite shipping of the first item to keep the installation order.
B. Rearrange the installation dates since other devices are already on site.
C. When the late equipment arrives, have the team work overtime.
D. Explain the vendor payments will be withheld if delivery is not met.
A. Expedite shipping of the first item to keep the installation order.
B. Rearrange the installation dates since other devices are already on site.
C. When the late equipment arrives, have the team work overtime.
D. Explain the vendor payments will be withheld if delivery is not met.