CompTIA Project+ PK0-004 – Question711

Which of the following should receive regular communication during the planning phase of a project? (Choose two.)

A.
Collaboration site
B. Change control board
C. Subject matter experts
D. Sponsor
E. Human resources

Correct Answer: CD