CompTIA Project+ PK0-004 – Question734

During a project, the project manager realizes some staff positions may be eliminated. Which of the following is the best NEXT step for the project manager to take?

A.
Communicate the concern with the project sponsor.
B. Identify replacement resources.
C. Review and update the project schedule.
D. Add the risk to the risk register.

Correct Answer: B