CompTIA Project+ PK0-004 – Question747

A project manager notices that project status meetings have been going awry. The project manager decides to limit the meetings to only those participants who have input. Which of the following should the project manager use to communicate to stakeholders who will no longer attend the meetings but need to be kept informed?

A.
Communication plan
B. Status report
C. Action items
D. Meeting minutes

Correct Answer: D