CompTIA Project+ PK0-004 – Question764

A vendor contacts the project manager regarding a particular component. The original scoped materials are no longer available, but the vendor has a replacement that can be used. Which of the following will MOST likely be impacted with the replacement material?

A.
Resources
B. Environment
C. Scope
D. Timeline

Correct Answer: D