CompTIA Project+ PK0-004 – Question768

A project stakeholder identifies a need for a vendor to provide 24-hour support for a product under development. Which of the following BEST describes where this information would be documented?

A.
Service-level agreement
B. Purchase order
C. Statement of work
D. Project charter

Correct Answer: A