CompTIA Project+ PK0-004 – Question787

A project manager is concerned that a planned change might damage the key functionality of a major system.
The MOST important activity to perform is:

A.
a quality control check.
B. an in-depth impact evaluation.
C. software version control.
D. a regression plan.

Correct Answer: B