A change request has been submitted to change the construction material from cinder block to wood frame.
Which of the following should be performed FIRST after the change has been approved by the sponsor?
A. Documentation update and review
B. Quality check
C. Team approval
D. Impact analysis
Which of the following should be performed FIRST after the change has been approved by the sponsor?
A. Documentation update and review
B. Quality check
C. Team approval
D. Impact analysis