CompTIA Project+ PK0-004 – Question796

A project team has deliverables that are scheduled to take several weeks to complete. The project manager is concerned that procrastination will set in. Which of the following should the project manager do?

A.
Allocate the resources.
B. Prioritize the tasks.
C. Review the milestones.
D. Set the dependencies.

Correct Answer: B