A project manager provides status reports to a customer on a biweekly basis, but the customer is very busy and only has a few minutes to review the project.
Which of the following are critical for the project manager to provide?
A. Cost, schedule, organizational chart, and risks/issues
B. Risks/issues, cost, RACI chart, and action items
C. Schedule, cost, risks/issues, and milestones
D. Action items, organizational chart, schedule, and NDA