Which of the following is a schedule that illustrates the duration of an activity? A. Process diagram B. Ishikawa diagram C. Gantt chart D. Pareto chart
Correct Answer: C
Explanation:
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 168