A project manager is attempting to establish the proper sequencing and duration of project activities.
Which of the following would be the MOST beneficial?

A.
Network diagram
B. Ishikawa diagram
C. WBS
D. Gantt chart

Correct Answer: A

Explanation:

Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 160