CompTIA Project+ PK0-004 – Question005 A project manager is creating the WBS. In which of the following phases is the project?A. InitiationB. PlanningC. ExecutionD. Closing Show Answer Hide Answer Correct Answer: B Explanation: Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 139 Post navigation CompTIA Project+ PK0-004 – Question004CompTIA Project+ PK0-004 – Question006