CompTIA Project+ PK0-004 – Question009

A stakeholder is unaware of a project's status.
Which of the following documents should the project manager consult to ensure all stakeholders are notified of project changes? (Choose two.)

A.
Status report
B. Organizational chart
C. RACI matrix
D. Meeting minutes
E. Communication plan

Correct Answer: AD

Explanation:

Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 261