During the initiation phase, a project manager has asked for a document containing the high-level objectives and goals for a project.
Which of the following documents would contain these items?
A. Business case
B. Requirements document
C. Project timeline
D. Task plan
Which of the following documents would contain these items?
A. Business case
B. Requirements document
C. Project timeline
D. Task plan