CompTIA Project+ PK0-004 – Question029

A carpenter on a project team reports there is insufficient time to accomplish tasks on schedule.
Which of the following is the FIRST step the project manager should take?

A.
Assess the risk register's new items.
B. Review the task start and finish dates.
C. Obtain additional resources.
D. Analyze the assigned hours.

Correct Answer: A