CompTIA Project+ PK0-004 – Question045

The client accepts the critical design review.
Which of the following meetings should be held to move to the NEXT step in the project?

A.
Execution
B. Kickoff
C. Closure
D. Planning

Correct Answer: B

Explanation:

Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 112