CompTIA Project+ PK0-004 – Question049

Which of the following documents should be used to provide high-level reporting to key stakeholders?

A.
Dashboard
B. Communication plan
C. Statement of work
D. Project charter

Correct Answer: A

Explanation:

Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 325