CompTIA Project+ PK0-004 – Question050

A new project charter is being drafted.
Which of the following would be the BEST source for the high-level project requirements?

A.
Sponsor
B. Project manager
C. Project management office
D. Project team

Correct Answer: A

Explanation:

Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 108