A project manager received a change request, immediately documented the required changes, and evaluated the impact of and justification for the changes.
Which of the following should the project manager do NEXT?
A. Gain approval for the changes.
B. Identify the approval authority.
C. Implement the changes.
D. Create an emergency change request.
Which of the following should the project manager do NEXT?
A. Gain approval for the changes.
B. Identify the approval authority.
C. Implement the changes.
D. Create an emergency change request.