CompTIA Project+ PK0-004 – Question092

Which of the following is the MOST likely target audience to be notified of the achievement of a key milestone in a project schedule?

A.
Project manager and project scheduler
B. Project coordinator and project sponsor
C. Project champion and project scheduler
D. Project stakeholders and project team

Correct Answer: D

Explanation:

Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 326