CompTIA Project+ PK0-004 – Question094

A senior manager asks a project manager for an estimated budget on a new project.
Which of the following is the BEST step for the project manager to take?

A.
Tell the senior manager the estimation is not available yet.
B. Use the budget from a similar project to generate estimates.
C. Ask a SME for an opinion and propose an estimate.
D. Gather the team to immediately generate estimates.

Correct Answer: B

Explanation:

Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 164