A project is about to begin the execution phase. The SOW and project plan have been approved, and the project team has been formed. Which of the following types of meetings should happen NEXT?
A. Update
B. Scheduling
C. Kickoff
D. Review
A. Update
B. Scheduling
C. Kickoff
D. Review