CompTIA Project+ PK0-004 – Question122

A software development project is struggling with a certain technology that is unknown to the project team. A project manager has received a third-party proposal to transfer the risk. Which of the following should the project manager do NEXT?

A.
RF1
B. RFP
C. RFQ
D. Change request
E. Request for bid

Correct Answer: E