CompTIA Project+ PK0-004 – Question126

A project manager has been assigned a complex project and does not know all the activities required to complete it.
Which of the following if the BEST approach to determine the work packages for the WBS?

A.
Brainstorming
B. Analogous
C. Bottom-up
D. Forward pass

Correct Answer: C