CompTIA Project+ PK0-004 – Question134

A team member was assigned a new task during a meeting. The team member did not complete the task by the end of the phase, and the PM is looking for evidence to escalate the issue. Which of the following documents could help in this situation?

A.
Issue log
B. Action items
C. Dashboard information
D. Communication plan

Correct Answer: A