CompTIA Project+ PK0-004 – Question143

A project manager is informed that a team member would like to enhance the code with an additional function.
Which of the following should the project manager do NEXT?

A.
Submit a change request.
B. Evaluate the impact of the change.
C. Get approval from the CCB.
D. Communicate the change to stakeholders.

Correct Answer: B