Using Scrum, which of the following are discussed in a daily standup meeting?
A. What was done yesterday, what is planned for today, and what roadblocks need to be removed
B. What was done yesterday, what is planned for the week, and what issues were resolved
C. What was done yesterday, what is planned for today, and what deliverables were completed
D. What was done yesterday, what is planned for this week, and what items from the backlog are priority
A. What was done yesterday, what is planned for today, and what roadblocks need to be removed
B. What was done yesterday, what is planned for the week, and what issues were resolved
C. What was done yesterday, what is planned for today, and what deliverables were completed
D. What was done yesterday, what is planned for this week, and what items from the backlog are priority