CompTIA Project+ PK0-004 – Question154

A company hires a number of interns and assigns them key roles on a project. Which of the following should the project manager MOST likely anticipate?

A.
Reduced quality
B. Reduced scope
C. Reduced risk
D. Reduced timeline

Correct Answer: A