CompTIA Project+ PK0-004 – Question161 A project team has finished creating a WBS and started developing a schedule. The team should FIRST determine the:A. durations.B. tasks.C. critical path.D. resources. Show Answer Hide Answer Correct Answer: B Post navigation CompTIA Project+ PK0-004 – Question160CompTIA Project+ PK0-004 – Question162