A. The reduced timeline will impact the quality of the deliverables because the amount of time to test will be reduced.
B. The reduced budget will result in reduced resources, which will lead to a strong matrix organizational structure being used.
C. The reduced timeline will decrease risk, resulting in an increased contingency reserve.
D. The reduced budget will cause the project manager to reject the change order.