A project manager is creating the monthly report for top management. The project manager has collected the information below:
AC = 100
PV = 80
EV = 120
Based on this information, the CPI reflects which of the following about the project?
A. It is under budget.
B. It is over budget.
C. It is ahead of schedule.
D. It is behind schedule.