CompTIA Project+ PK0-004 – Question178

The business stakeholder has been engaged late and has just had a chance to review the approved requirements. Consequently, it has been identified that there are a number of gaps in the requirements which are critical to the stakeholders's business unit.
Which of the following actions should the project manager take?

A.
Initiate change control.
B. Follow communications plan.
C. Manage project quality.
D. Prepare a performance report.

Correct Answer: A