Which of the following should the project manager do to ensure stakeholder expectations are met?
A. Ensure that Ann is involved during the testing phase of the project so she can call out functional gaps.
B. Organize a walkthrough of the solution and ensure face-to-face updates occur every two weeks.
C. Escalate the issue to the project steering committee that Ann is criticizing the project quality.
D. Organize a requirements workshop to capture any gaps.