CompTIA Project+ PK0-004 – Question188

Which of the following techniques modifies the schedule based upon resource constraints?

A.
Critical Chain Method
B. Critical Path Method
C. Arrow Diagramming Method
D. Precedence Diagramming Method

Correct Answer: A