CompTIA Project+ PK0-004 – Question193

The project's network map has a loop with multiple project outcomes.
This is the result of which of the following scheduling tools?

A.
Establishing project schedule baselines
B. Critical Path Analysis
C. Critical Chain Method
D. Graphical evaluation and review technique

Correct Answer: D