CompTIA Project+ PK0-004 – Question197

A PM receives notification that an issue will impact a deliverable on the critical path. The issue is logged with a unique ID and assigned to a team member; however, the team member has not addressed it after a week.
Which of the following would be the BEST approach to resolving the issue?

A.
Assign a different team member to resolve the issue before the next status meeting.
B. Review the issue with the assigned team member to determine a due date.
C. Set a due date to resolve the issue and inform the assigned team member.
D. Report the team member to a functional manager for disciplinary action.

Correct Answer: B