A project manager is not required to participate in performance appraisal meetings with team members. The project manager is working within which of the following organizational structures?
A. Projectized
B. Balanced matrix
C. Functional
D. Strong matrix
A. Projectized
B. Balanced matrix
C. Functional
D. Strong matrix