CompTIA Project+ PK0-004 – Question202

A new stakeholder has requested the status and progress reports for the project milestones. Which of the following documents should the project manager address FIRST?

A.
Project communication plan
B. Project status report
C. Project management plan
D. Project backlog

Correct Answer: C