CompTIA Project+ PK0-004 – Question211

A minor change to the baseline schedule is required. This change will be the second minor modification to the schedule. Which of the following is the appropriate version number?

A.
0.3
B. 1.2
C. 2.0
D. 3.0

Correct Answer: B