During the storming stage of a project team's development, it is common to experience confusion about tasks and responsibilities because:

A.
there is unfamiliarity with the project structure.
B. there is a lack of trust among team members.
C. there are minimal team decisions.
D. there is no engagement of the team by the project manager.

Correct Answer: B

Explanation: