CompTIA Project+ PK0-004 – Question218 A project manager procures additional resources from a local company. Which of the following-describes this event?A. ReorganizingB. OnboardingC. OffshoringD. Outsourcing Show Answer Hide Answer Correct Answer: A Post navigation CompTIA Project+ PK0-004 – Question217CompTIA Project+ PK0-004 – Question219