CompTIA Project+ PK0-004 – Question226 Which of the following are mutually binding project documents? (Choose two.)A. QuotationB. Letter of intentC. ProposalD. EvaluationE. WarrantyF. Charter Show Answer Hide Answer Correct Answer: BF Post navigation CompTIA Project+ PK0-004 – Question225CompTIA Project+ PK0-004 – Question227