CompTIA Project+ PK0-004 – Question246

A change is being implemented on a project, and while in testing, it becomes clear that the change cannot be finalized due to the severe impact it would have on other critical systems. Which of the following should the team consult to determine which actions to take?

A.
Incident response plan
B. Regression plan
C. Progress plan
D. Business continuity plan

Correct Answer: D