Which of the following is the MOST likely reason the project manager would be unaware of the team member's decreased morale?
A. The project manager did not pay attention to visual cues.
B. The project manager did not perform active listening.
C. The project manager did not prioritize team member concerns.
D. The project manager did not visit the project's international office locations.