CompTIA Project+ PK0-004 – Question255

A vendor advises the project manager that a key component of the project is no longer available and recommends a higher-cost replacement. To have this change approved, the project manager submits a change request that contains which of the following?

A.
Description, cost difference of the replacement, and WBS
B. Description, justification, and cost
C. Cost difference of the replacement, justification, and communications plan
D. Description, quality impact, and cost

Correct Answer: B